A look ahead for January 2020
Hospital Buildings 
> Piling works ongoing to Forensic Building 
> Bulk excavation to Non-Forensic Building with muck shifting to park area 
> Commencement of foundation works to hospital buildings 
> Tower Crane installation commencing adjacent to new hospital buildings 
Civil and Infrastructure 
> Bulk excavation, ongoing tree removal and hoarding erection to former golf course including topsoil strip 
> Continuing plot preparation for handover to residential developer
> Demolition to former Golf Club House to commence with asbestos removal
> Hoarding to residential building plots commencing adjacent to Harewood House and then continuing to plots along newly installed Springfield Drive
> Site welfare cabin installation ongoing to site compound area 
> Construction entrance off Burntwood Lane is now live 
> Continued road construction to Springfield Drive outside Harewood House to Gate Lodge 
> Preparation works underway for nursery playground relocation
 
          
        
      