A look ahead for August 2020
Hospital Buildings
- Ongoing construction of foundations and concrete frame work to Forensic and Non-Forensic hospital buildings 
- Ongoing closure and re-diversion to Storey Building main reception entrance until mid-September to facilitate the ongoing construction of the Forensic building 
- Commencement of façade installation to Non-Forensic building 
- Ongoing work to Energy Centre including demolition and preparation for structural works 
Civil and Infrastructure
- Ongoing Road 4 construction within current road closure adjacent to plots P and Q 
- Ongoing earthworks to Park Area B and C (old golf course) 
- Outfall drainage installation to commence in park area 
- Ongoing hoarding installation along Burntwood Lane 
August 2020 Works Location Drawing
 
          
        
      