Barratt London will carry out following activities on Saturday 23rd October:
- 2no. forklifts moving materials – site wide 
- Brickwork & blockwork at B1A ,B2A, C1A, C2A, L&M 
- Ground works to parcel E1A & E2B, Gate M 
Bricklayers will cease all works at 1pm. Ground workers and Barratt staff will remain on site till 3:30pm and carry out low noise activities.