A look ahead for June 2022
Hospital Buildings (Delivered by Sir Robert McAlpine)
- Trinity (Non-Forensic) building’s façade is now complete. The Shaftesbury (Forensic) façade is still ongoing but nearing completion. 
- There are ongoing fitout works to Shaftesbury and Trinity hospital buildings. 
- Mechanical and Electrical works ongoing to both Shaftesbury and Trinity buildings. 
- All scaffolding has now been struck on both the Trinity and Shaftesbury buildings. 
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
- Park works will be finishing in June with landscaping and grass seeding being completed. Resin is being applied to all the footpaths. 
- Tree and shrub planting is complete in the park area and maintenance will be occurring with watering. 
- Construction is progressing outside Mayfield Nursery and Gymnastics Club and both new hospital buildings, but uninterrupted access will be maintained for both parties through Share Garden. 
- Works to progress hard landscaping on Springfield Drive is ongoing. 
SRM Works Location drawing for June 2022
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
- M - Occupations commence 15th June 2022 
- Soft landscaping to be completed and area now opened up 
 
- L - Internal works continue 
- Service connections being worked on to footpath on Glenburnie Road 
- Balconies installed 
- Remove all hoarding 
- Block to CML 
 
- B – C - Internal works progress 
- Balcony install to C1A 
- Hard landscaping continues and will be complete to B within the next month 
- Soft landscaping commence 
- C2A to progressive strike to commence 
 
- E1/E2 - Superstructures continue up to 1st and second floors 
 
- D2 - D2C superstructure to commence 
 
Barratt detailed Execution Plan
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
- First Fix, Close Up, Plaster, 2nd Fix, Decoration and Finals to apartments. 
- Completion of apartments and communal areas. 
- Scaffold strike to remaining blocks. 
- External finishes. 
- Hard and soft landscaping. 
- Legal completions. 
- Occupations 
Phase 2
- Demolition works ongoing. 
- Drainage and services. 
- Scaffold erection and adaptions. 
- Structural alterations and repairs. 
- Roofing works. 
- Masonry repairs and cleaning 
New care home facility - Plot H (delivered by Lawrence Baker)
- Remove the crane from site. Confirmed for 16th & 17th June 
- Complete the feature brick openings to the North Elevation – Steels to be erected Monday 20th June 
- Complete the plastering works to the lower ground floor area 
- Complete all internal finishes to the bedrooms on the upper two floors 
- Complete all external hard landscaping to the North & South elevations 
- Aiming to have all incoming services, water, electricity, and district heating connected 
- All scaffolding will be removed 
- All cladding feature panels to be completed. 