A look ahead for August & September
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
- The park (area B) is open. 
- Public access is opened on Springfield Drive and Chapel Square. Car parks in the new hospitals are open. 
- The entrance to Burntwood Lane is OPEN for both vehicle and pedestrian access. 
- Park area A is completed and currently maturing. The pavilion is nearing completion too. Park area A is due to open October 2024, after a period of maturing. 
- Harewood House plot handed over to the House Developer (London Square) in June 2024. 
- Park C works is complete except for seeding which has been deferred to ensure seeding occurs at the correct time of the year. Park area C is due to open October 2024, with areas cordoned off to allow maturing. 
- District heating works down to X,Y,Z plot is progressing and reinstatement of footpath is nearly complete. Will be completed early August 2024. 
- Road 4; Lapidge Drive is completed and open for access to everyone. 
- The last substation build within the development is completed outside Phoenix Building. Infrastructure works is completed to allow energisation early August 2024. 
Residential Phase - Plots B-E and L&M (delivered by Barratt London)
- D2C Occupied 
- E1 Occupied 
- E2 Occupied 
- D1A internal fit out has commenced Balcony install to commence late July, Granit paving commenced, Handover to Sainsbury End of August 
- D1B, Occupied 
- D1C Occupied 
- D2B Occupied 
- D2A Roof slab due early August, fit out to commence in September 
- D parcel (Cherry mews) Open 
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
Complete
Phase 2
- Scaffold adaptions and strike 
- Structural alterations and repairs 
- Roofing works to Orchid Wing 
- Re-Facing of brickwork elevations 
- Masonry repairs and cleaning 
- Window refurbishment 
- Test and commissioning 
- Handovers and completions within Kitchen Block, Engineering Tower & Dormitory Wing 
- Internal fit out ongoing to Dormitory and Orchid wing 
- Hard & Soft Landscaping. 
Next phase of new build residential Plots G, P, Q and F (delivered by London Square)
Block P
- House basements complete. 
- Commenced super structure brickwork to the apartment block 
- Installing the beam and block floor to the apartment block. 
- Commenced setting out & 2nd lift scaffold. 
Block Q
- Commenced the basement excavation to the houses. 
- Commenced basement slabs and walls to the houses. 
- Ground beams to block Q1 & Q2 apartment block in progress 
Block G
- Existing substation has been deenergised and removed and the new substation energised and in use. 
- Installing the beam and block floor to the G1 & G4 apartment block. 
- Continue brickwork to G2/3. 
Block F
- SRM handed over block F to LSQ, with demolition and piling works to commence. 
External CGI from London Square Apartment overlooking Springfield Park
Area of Responsibility Plan
 
          
        
       
             
            