A look ahead for October & November
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
- The park is open (with areas in Park area C cordoned off to allow maturing). 
Residential Phase - Plots B-E and L&M (delivered by Barratt London)
Total number of plots sold to date is 243 with 35 plots remaining.
Primrose House (D2A) is fully occupied.
Works taking place during October and November: D1A internal fit out continues to complete mid-October, D2A both internal and external work progressing,
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1 is complete.
Works continue on Phase 2, which include:
- Demolition to the final section of existing roof to Orchid Wing 
- Installation of new steel and timber frame to roof to Orchid Wing 
- Re-Facing of brickwork elevations 
- Masonry repairs and cleaning 
- Window refurbishment 
- Test and commissioning to apartments within Kitchen Block, Engineering Tower & Dormitory Wing apartments 
- Internal fit out and commisioning to communal areas above 
- Building Control / warranty provider inspections and certification for units ready to handover to purchasers in Kitchen Block, Engineering Tower & Dormitory Wing 
- Hard & Soft Landscaping to external areas 
Currently on Phase 3 City & Country are doing preparation works for a new office facility for Share Garden in anticipation of decanting from Phase 3 areas. There are also improvements to access and hoarding works in advance of construction activity starting on site.
Next phase of new build residential Plots G, P, Q and F (delivered by London Square)
Sales
· 8 - plots have currently been sold which include 4 x two bed apartments and 4 x houses.
Block P
- Completion of 2nd floor structural balcony brackets 
- Commence 5th lift brick work 
- Commence roof trusses to plots 230 to 233 
- Commence 2nd floor joists to plots 234 to 236 
- Commence 1st floor joists to plots 237 to 240 
Block Q
- Commence 1st lift brick work 
- Commence 1st lift scaffold 
- Commence district heating to Q houses 
- Commence 1st lift brick work to plots 242 to 244 
- Commence the installation of services & permeable road to plots 242 to 250 
Block G
- Commence 3rd lift brick work to block G2 & 3 
- Installation of block G1 & 4, 1st floor pre-cast planks 
- Continue brickwork to G2/3. 
Block F
- Commence block & beam to both block & houses 
- Commence external services and drainage. 
- Installation of tower crane on 28/11/24 
External CGI from London Square Apartment overlooking Springfield Park