New homes - Construction update

Residential Phase - Phase 2B (delivered by Barratt London)

The new sales and marketing suite for The Lanes development on Plots X, Y & Z has now launched. Feel free to pop in and say hello.

  • Upcoming works to Parcel 1 as shaded red on the plan below.

    • Demolition to the existing hospital buildings is now complete.

    • Enabling works have commenced.

    • Targeting to start Piling in October.

  • Formation of foundations and groundworks to start following completion of Piling.

    • The erection of two tower cranes to assist with the loading out of materials is planned before the end of the year.

Conversion of listed main building to residential - Plot S (delivered by City & Country)

Phase 1 is complete.

Current occupations at the 1840 is 80 in total

Phase 2

Central area comprising of Engineering Tower, Boiler House Units and Dormitory Wing are now complete and residents in occupation. Upcoming activities:

  • Central Area – Engineering Block Units fit out in progress

  • Orchid Wing - Approximately 50% build complete and occupied, with cores being completed from West to East. Fit out ongoing and progressive build complete with legal completions until November 2025

  • External Works – Utilities and landscaping from West to East

Majority of C&C staff to relocate to Building 32, with Lapidge Drive site cabins to be decanted at the end of September (Satellite site facilities to remain in situ).

Phase 3

  • Continuation of asbestos removal / soft strip / demo to all blocks

  • Ground works / utilities to start

  • Structural alterations to start

Next phase of new build residential Plots G, P, Q and F (delivered by London Square)

Sales

  • 32 plots have currently been sold which include 12 houses and 20 apartments.

  • Occupations to Plot P to commence 25th September 2025.

Block P

  • Plot P houses are at various stages of completion.

Block Q

  • Scaffold being removed with external services and ground works to follow

  • Internal fit out on-going

  • Lifts installation in progress

  • Plot Q Houses 242 to 249 various stages of 1st fix and closure

  • Plot Q Houses 250 – 253 roof finishes in progress with window install to follow

Block G

  • Scaffold being removed with external services and ground works to follow

  • Internal fit out on-going

  • Communal corridor fire stopping in progress

  • Window installation in progress

Block F

  • Roof and window finishes in process

External CGI from London Square Apartment overlooking Springfield Park