New homes - Construction update
Residential Phase - Phase 2B (delivered by Barratt London)
The new sales and marketing suite for The Lanes development on Plots X, Y & Z has now launched. Feel free to pop in and say hello.
Upcoming works to Parcel 1 as shaded red on the plan below.
Demolition to the existing hospital buildings is now complete.
Enabling works have commenced.
Targeting to start Piling in October.
Formation of foundations and groundworks to start following completion of Piling.
The erection of two tower cranes to assist with the loading out of materials is planned before the end of the year.
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1 is complete.
Current occupations at the 1840 is 80 in total
Phase 2
Central area comprising of Engineering Tower, Boiler House Units and Dormitory Wing are now complete and residents in occupation. Upcoming activities:
Central Area – Engineering Block Units fit out in progress
Orchid Wing - Approximately 50% build complete and occupied, with cores being completed from West to East. Fit out ongoing and progressive build complete with legal completions until November 2025
External Works – Utilities and landscaping from West to East
Majority of C&C staff to relocate to Building 32, with Lapidge Drive site cabins to be decanted at the end of September (Satellite site facilities to remain in situ).
Phase 3
Continuation of asbestos removal / soft strip / demo to all blocks
Ground works / utilities to start
Structural alterations to start
Next phase of new build residential Plots G, P, Q and F (delivered by London Square)
Sales
32 plots have currently been sold which include 12 houses and 20 apartments.
Occupations to Plot P to commence 25th September 2025.
Block P
Plot P houses are at various stages of completion.
Block Q
Scaffold being removed with external services and ground works to follow
Internal fit out on-going
Lifts installation in progress
Plot Q Houses 242 to 249 various stages of 1st fix and closure
Plot Q Houses 250 – 253 roof finishes in progress with window install to follow
Block G
Scaffold being removed with external services and ground works to follow
Internal fit out on-going
Communal corridor fire stopping in progress
Window installation in progress
Block F
Roof and window finishes in process
External CGI from London Square Apartment overlooking Springfield Park
Area of Responsibility Plan